From Blueprint to Reality: Project Update on Montrose County North Campus Building as of 07/24/2026

Montrose County

Mirrored from montrosecounty.net, last checked August 28, 2026. This is a courtesy copy, not the official record. Confirm dates and deadlines with Montrose County before acting on them.

Published July 29, 2026 Montrose County

At a glance

Montrose County North Campus Building construction updates show exterior wall finishing, drywall installation, and panel work progressing as of July 24, 2026.

West Side- exterior wall is ready for finish applications

Third Floor - drywall installation in progress

Southwest Corner - stucco final color coating and stone finish installation are nearing completion

Northwest Corner - ACM panel installation has started

Main Lobby Area - painting activities are progressing

Photos Courtesy of Stryker & Co., Inc.