From Blueprint to Reality: Project Update on Montrose County North Campus Building as of 08/14/2026

Montrose County

Mirrored from montrosecounty.net, last checked September 3, 2026. This is a courtesy copy, not the official record. Confirm dates and deadlines with Montrose County before acting on them.

Published August 19, 2026 Montrose County

At a glance

Montrose County North Campus Building project update as of August 14, 2026 details ongoing drywall, stucco, and ACM panel installation.

Stairwell - drywall installation is progressing

Southeast View - Stucco cement base coat is ongoing as well as other exterior finishes

South View - the exterior continues to take shape

Northwest View - ACM panel installation is gaining good progress

Ground Floor - door and hardware installation is progressing

Fire riser assembly is shown and leak testing is in progress

East View - exterior finishes are progressing
Photos provide by: Stryker & Co., Inc.