Montrose County North Campus building construction update reports concrete work started, millwork completed, front entry walls poured, and east side sills installed as of September 25, 2026.

Concrete work has begun around the outside of the building.

Second floor conference room.

Millwork being completed near open offices.

Front entry site walls have been poured.

East side of building - concrete and precast sills being installed.

Photos provided by Stryker & Co., Inc.