Orange Cone Report for the week of October 19, 2026

City of Durango

Mirrored from durangoco.gov, last checked October 19, 2026. This is a courtesy copy, not the official record. Confirm dates and deadlines with City of Durango before acting on them.

Published October 16, 2026 La Plata County

At a glance

The weekly Orange Cone Report details traffic impacts from the Roosa Safety Project, Animas River Trail Phase 2, Wilson Gulch Drive, and US 160 for the week of October 19, 2026.

Durango, CO: **The City of Durango's Orange Cone Report is designed to inform motorists about construction projects and events that may cause traffic delays. Each week, an interactive map will be updated on the city's social media channels and website.

To receive an email with the Orange Cone Report, go to the city's NotifyMe notification system and select "City of Durango News Flash."

Construction projects and events that will impact traffic the week of October 19: Roosa Safety and Connectivity Project **

Project Summary:
The project includes approximately 1,300 feet of new sidewalk on the east side of Roosa Avenue and 9th Street to the Riverbridge Apartments; intersection improvements at Avenida Del Sol and El Paso Street; protected bike lanes; ADA ramp upgrades; transit stop improvements; asphalt milling and overlay; and updated pavement markings to reconfigure traffic flow. The project is expected to be completed by the end of November.

  • Lane width limitations and possible closures will be in effect along Roosa Avenue between 9th Street and El Paso Street.

  • Avenida Del Sol will be closed for underground utility work with a detour in place.

  • Traffic lanes have been shifted along Roosa Avenue between 9th Street and Avenida Del Sol.

  • The transit stop near Manna Soup Kitchen remains open.

  • Daytime work hours range from 7 a.m. to 5 p.m., Monday through Friday.

  • Traffic will be reduced to one lane in both directions on Roosa Avenue during working hours.

Animas River Trail Phase 2 (see below for map)

  • Phase 2 has started on rebuilding the spur trail between the Animas River Trail and Rio Vista Circle. The spur trail will be closed.

  • Demon Bridge will remain open during this portion of the construction. Crews will be constructing the abutments in preparation for the new bridge installation for next spring.

  • Additional vegetation clearing will take place on the west side of the river in accordance with environmental permit requirements to protect the endangered New Mexico meadow jumping mouse. The clearing is being conducted proactively to discourage the establishment of winter hibernation nests in the project area and will occur under the direction of environmental specialists.

  • Trail users should follow the detour signs.

  • This phase is expected to continue for 2-3 months.

Wilson Gulch Drive (see below for map)
Project Summary:
New utility infrastructure will be extended to the current Spur Line Trailhead, and the existing gravel road will be replaced with a new two-lane paved roadway featuring a raised median. Once complete, the new pavement will extend past the trailhead and connect to Prospector Avenue (East). This work precedes the construction of the upcoming Three Springs Elementary School for the Durango School District. Construction is anticipated to last through November.

  • Starting at the roundabout at Confluence Avenue, Wilson Gulch Drive is closed for major road and utility upgrades.

  • Public trail access will remain available through the project. Parking will be permitted along the south side of Prospector Avenue.

US Highway 160 at Elmore's Corner (Colorado Department of Transportation CDOT project)
Project Summary:
Work will include resurfacing the highway, striping, new delineators, guardrail, and road sign replacement. The Durango High Bridge will undergo deck repairs and new resurfacing. New ramps, compliant with the Americans with Disabilities Act, will be installed on US Highway 160 at Dominguez Drive, River Road, Three Springs Boulevard, and Colorado Highway 172/County Road 234 (Elmore’s Corner).

  • Paving and milling operations will continue between Three Springs and Highway 3.

  • Paving and milling in this area are expected to take three weeks.

  • Most work will occur at night, but motorists may experience daytime delays and congestion due to lane closures and traffic shifts that will remain in place 24/7.

  • Motorists can expect daytime delays in both directions to continue throughout the summer as milling and paving operations progress towards Walmart.

Click on the map below to interact.

WE WANT TO HEAR FROM YOU!

Do you have a comment, question, or suggestion? Let us know through our “Contact Us” form. Want to receive releases on city news? Sign up for Notify Me and select "City of Durango News Flash."


Media Contact**Nicolette Iron ShellPublic Works Administrative Specialist Email: [email protected]