Meadow Lane to Close for Culvert Replacement and Upgrade - Through Approximately October 25
Four-Week Closure For Critical Stormwater Improvements
**Steamboat Springs, Colorado-September 14, 2026-**Meadow Lane will be closed to through traffic for approximately four weeks beginning September 28, 2026 as the city replaces and upsizes a culvert beneath the roadway to improve stormwater capacity and reduce the risk of street overtopping and washout.
The drainage infrastructure project will replace the existing culvert that carries flows from the Bear Creek Tributary, a tributary of Walton Creek. The upgraded culverts are intended to improve stormwater flow and limit potential impacts to nearby homes and properties during significant storm events.
The project will begin construction this fall, with the Meadow Lane closure beginning Monday, September 28, 2026. Construction is expected to take approximately four to five weeks, with the full closure of Meadow Lane lasting approximately four weeks.
During the closure, both lanes of Meadow Lane will be closed at the project site to all through vehicular, pedestrian and bicycle traffic. Detours will be provided, and access to surrounding residences and businesses will be maintained throughout construction.
Additionally, Steamboat Springs Transit (SST) will temporarily modify its bus service during the Meadow Lane closure. Bus stops on Village Drive south of Walton Creek Road and all Meadow Lane stops will not be serviced during construction. The four affected stops are:
Alpine Ridge/Meadowlark
Sunray Meadows/Sunburst
Bear Drive
Timothy Drive
Passengers who normally use the Meadowlark or Sunray Meadows stops should use Trappeur’s Crossing as an alternate stop. Those who normally use the Bear Drive or Timothy Drive stops should use Whistler Park as an alternate stop. Normal SST bus operations will resume once construction is complete.
Sanitary Sewer Replacement Closes Rollingstone Drive - October 5 through October 31, 2026
Project Anticipates Four-Week Closure For Critical Infrastructure Improvements
**Steamboat Springs, Colorado-September 30, 2026-**Rollingstone Drive will close to through traffic beginning Monday, October 5, for a sanitary sewer replacement project expected to take up to four weeks.
“Replacing aging and underperforming infrastructure is an important part of maintaining a reliable sewer system for the community,” said Public Works Director Jon Snyder. “Projects like this allow us to address infrastructure needs before they become larger problems, while helping ensure the system continues to serve residents safely and reliably.”
The closure will affect Rollingstone Drive between Pine Grove Road and Anglers Drive. Motorists will not be able to use Rollingstone Drive to travel between those two roads during construction.
The project will begin at the entrance to Sundance Condominiums and continue south across Anglers Drive and along Rollingstone Drive to the northern intersection of the Selbe Apartment driveway. Residents of Anglers Retreat must use Anglers Drive to enter and exit the subdivision during construction.
The project will replace an underperforming sanitary sewer main, including approximately 448 linear feet of existing 6-inch and 8-inch PVC sanitary sewer main and associated services. The work will install new 6-inch and 8-inch PVC sewer main along Rollingstone Road.
Construction activity will be limited to 7 am to 7 pm, Monday through Friday. The road is expected to remain closed to through traffic for up to four weeks, depending on construction conditions. Motorists are encouraged to plan for the closure and use alternate routes while work is underway.