Hunter Fire · Wildfire · Rio Blanco County · yesterday

Details

Public notice

Projects Affecting Traffic for the Week of July 20, 2026

City of Grand Junction

Mirrored from gjcity.org. This is a courtesy copy, not the official record. Confirm dates and deadlines with City of Grand Junction before acting on them.

Published July 16, 2026 Mesa County

At a glance

City of Grand Junction lists travel restrictions for multiple road improvement projects and non-city projects affecting traffic during the week of July 20, 2026.

City of Grand Junction Projects with Travel Restrictions

Crossby Avenue Improvements Project

  • Crosby Ave. will be closed between W. Main St. and American Way.

  • Business and local traffic access will be maintained.

Four Canyons Parkway Project

  • 25 Rd. will be closed between Flat Top Lane/Foresight Cir. and Blichmann Ave.

  • F 1/4 Road is closed to through traffic from 25 Rd. to Zenith Lane. Residents' access remains open.

  • Two-way traffic on 25 Rd. open from Patterson Rd. to Flat Top Ln. on a gravel surface.

  • 24 ¾ Rd. Northbound traffic is no longer able to pass through Four Canyons Parkway.

  • 25 Rd. Remains closed between Blichmann Ave. & F ½ Road.

D 1/2 Rd. Capacity Improvements Project

  • D ½ Rd. will be closed between 29 Rd. and 30 Rd. Access will be maintained for local traffic.

  • Access to and from San Juan St. will be closed at the intersection of San Juan St. and D ½ Rd.

  • Detours are in place; access to San Juan is available via 29 ½ Rd. from D Rd.

Patterson & 28 ½ Rd. (Matchett Parkway-entrance to Rec. Center)

  • Sidewalk along the North and South side of Patterson Rd. is now open between 28 ¼ and 28 ¾ (Legends Pkwy.). Pedestrians crossing Patterson will continue 28 ¼.

  • Lane closures are in place beginning June 22.

  • Alternate routes are advised.

Non-City Project with Travel Restrictions

  • CDOT - Ute & Pitkin Improvements (I-70B East of Third Street Imp. Project)

  • 5th St. will be reduced to one lane between South Ave. and Colorado Ave.

  • Single lane closures and shoulder closures will be in effect on Ute Ave. and Pitkin Ave. between 3rd St. and 6th St.

  • 4th St. will be reduced to a single lane between Colorado Ave. and Pitkin Ave.

  • All business and residential access will remain open.

  • Parking and access in alleys will remain open.

  • For questions or concerns, call 970-880-0688 or email [email protected]

  • CDOT CO 340 - Overlay Between Redlands Parkway & Grand Avenue

  • Lane closures will be implemented for eastbound and westbound traffic across the Hwy. 340 bridge.

  • Crews will be working overnight between 7 p.m. and 7 a.m. Monday through Friday.

  • 23 Road & Broadway Roundabout

  • Alcove Drive will be closed at 23 Rd., with detours via Vista Grande Rd. or Columbine Drive to access 23 Rd.

  • Alcove will remain closed for the duration of the project.

  • CO 340 will remain two-way traffic with a 35 MPH speed limit in the work zone.

  • Sidewalk access will be maintained. Please stay clear of active work areas.

  • Expect delays.

More from City of Grand Junction