**STEAMBOAT SPRINGS, COLORADO-October 7, 2026-**As the days grow shorter and the first hints of winter are on the horizon, Public Works is reminding homeowners, builders, and contractors to plan ahead for winter construction projects and right-of-way impacts.
“Winter will be here before we know it, and now is the time to get ahead of the deadlines,” said Streets Superintendent David Van Winkle. “If you’re planning to continue construction through the winter, schedule your inspections and complete any required site work now. A little planning before November can help prevent delays and additional work when spring arrives.
Contractors and homeowners anticipating the need for a temporary certificate of occupancy (TCO), certificate of occupancy (CO), or water/sewer service during the winter months should schedule inspections, so grading, drainage, and utility work are completed before November 1.
Single-Family/Duplex Projects:
Final Site Inspections for CO or TCO must be scheduled through CityView before Nov 1.
Provide your name, project address, and building permit number.
Inspections are not available between November 1 and April 1, weather permitting.
Commercial, Industrial, or Multifamily Projects:
Final Engineering Site Inspections must also be scheduled via CityView with your name, site address, and building permit number.
Inspections are unavailable from November 1 through April 1, weather permitting.
Water and Sewer Connections (Single-Family/Duplex):
Schedule inspections early through CityView.
Outdoor water/sewer work is prohibited from November 1 – May 1 without a variance.
Work in the Right-of-Way (ROW):
Permits are required via CityView.
Excavation in the public ROW is prohibited from November 1 – May 1 unless a variance is approved by the Public Works Director.
Construction Site Requirements:
All dumpsters, port-o-johns, material piles, and similar items must be removed from the ROW by November 1 unless a ROW permit is approved.
Install and maintain all erosion and sediment control measures before winter. Protect disturbed soils with hydro-mulch, straw blankets, or other approved methods prior to November 1
Right-of-Way (ROW)
All landscaping materials, particularly rocks, located within six (6) feet of the roadway must be removed.
The right-of-way is designated for snow storage purposes. Loose materials within this area, such as rocks, can cause significant damage to snow removal equipment, result in costly repairs, and negatively affect snow removal operations.
Following these steps ensures projects stay on track, prevents disruptions to city operations, and helps homeowners and businesses avoid additional costs when spring arrives.
-WeServeTheCity-
Contact
Email David Van Winkle, Streets Superintendent, or call 970-879-1807
Email Tom Martindale, Streets Supervisor, or call 970-879-1807
Email Scott Slamal, Stormwater Specialist and Engineering Inspector, or call 970-871-8236