Vail Valley Foundation Approves $19M Amphitheater Phase Two
The Vail Valley Foundation approved phase two of a $19 million renovation for the Gerald R. Ford Amphitheater, with work starting in September and concluding by April 2027.

Aspen —“Phase two means for this venue and everyone who visits it each summer,” Mike Imhof, president and CEO of the Vail Valley Foundation, said Wednesday, his voice carrying the weight of a project that has already reshaped the physical landscape of the Vail Valley. The nonprofit’s board executive committee gave the green light to begin this next chapter of transformation in late September, locking in a timeline that sees work concluding by early April 2027.
It is a date chosen with deliberate care, arriving just in time for the Gerald R. Ford Amphitheater’s 40th anniversary season.
If you’ve walked past the venue recently, you might have noticed the fresh myrtle green upholstery of the new pavilion seats or felt the no-slip texture underfoot where concrete floors were repaired. Phase one, completed this spring by MacAllister Construction, laid the groundwork for comfort and accessibility. But phase two digs deeper into the operational bones of The Amp, expanding both the east and south concessions areas while enlarging the loading dock.
The goal is to make the mundane feel effortless. As David Kaselak, principal at Zehren and Associates and the lead architect on these improvements, noted, the work reimagines how guests move through the space. Arriving, gathering, and grabbing a bite should feel easier, more welcoming — a seamless transition from the parking lot to the seat.
There is a warmth to these upgrades, but they are also practical necessities for a venue that regularly hosts performances from April through October. The expanded loading dock will streamline load-in and load-out processes, reducing the logistical friction that often plagues large-scale productions. Meanwhile, upgraded utility infrastructure across the site ensures that the power and water systems can handle increased demand without faltering.
MacAllister Construction returns as the general contractor for phase two, a continuity that suggests stability in both labor and quality. The work is being strategically phased during the offseason months, ensuring that the community’s enjoyment of summer performances remains uninterrupted. This is not a construction zone that blocks your view; it is one that builds around the life of the valley.
When phase two wraps in April 2027, the third and final phase will take over. That final stretch includes a significantly expanded box office, renovated back-of-house areas like green rooms and dressing rooms, and a new two-story north concessions building featuring a multiuse studio and special event space. The entire $19 million project is set for completion by May 25, 2028.
Taken together, these renovations allow The Amp to meet the needs of artists and guests alike across a longer, more vibrant season. The venue aims to increase diverse programming by 25% during peak summer months, attracting iconic artists while maintaining its status as a home for the Bravo! Vail Music Festival and Vail Dance Festival.
As September approaches, you can feel the anticipation building in the gravel and timber of the amphitheater. It is a place that has hosted legends for four decades, and now it prepares to host them again, with wider aisles, better food, and a stage that feels ready for whatever comes next.